https://www.techtarget.com/searchdisasterrecovery/definition/change-control
Change control is a systematic approach that includes the various steps needed to process changes made to a product or system.
Completing change control methodically is part of a change management process. The purpose of change control and change control management is to ensure that no unnecessary changes are made, all changes are documented, services are not disrupted unnecessarily, and resources are used efficiently. Within IT, where processing changes is a daily activity, change control is a component of change management.
The change control process is usually conducted as a sequence of steps resulting from the submission of a change request. Typical IT change requests include adding features to software applications, installing patches, and upgrading network equipment or systems.
The following is an example of a six-step process for a software change request:
The following diagram shows a visual representation of the change request process.
The basic change control process is simple. Anyone can submit a change request. Once the request has been written and submitted, it is reviewed by the change management team. If approved, it might be analyzed further, or it can go directly to the change control board (CCB). Assuming the proposed change gets approved for processing, it goes through multiple steps that can include design, engineering, prototyping, hardware and software selection, acceptance testing, rollout into production and follow-up before the request can be closed.
The basic components of a typical change request are typically universal across industries, and include the following:
In a typical IT department, a change control board examines the proposed changes, assesses viability, recommends approval or rejection, and conducts subsequent reviews as the change progresses to completion. IT employees can be assigned to the CCB and also to one or more change management teams.
IT department employees are the most likely to submit change requests since they work with systems and networks daily. Any proposed change is first discussed with management. If the issue has merit, the employee prepares a change request signed by a manager and submits it to the change management team.
Company employees can also propose a change. Initial contact is with the help desk to establish a ticket for tracking. Then the request is queued for review by the change management team, which provides an initial review and assessment. The team might be authorized to reject a request without sending it to the CCB. If the team approves the request, a formal change document is prepared with a detailed description as specified in the change management policy. When the CCB meets, its members can discuss the request. If more information is needed, the request will be returned to the requestor. The updated request is then sent to the CCB for further discussion and to decide on the changes.
Change control is typically a good idea when one of the following conditions arise during project planning:
From an audit perspective, the change management process is a collection of specific controls, including change control, each of which contributes to the completion of a change. While the change process is typically depicted as a series of steps, the steps can also be considered controls for audit review.
The following diagram depicts a change management process and several of its controls.
The diagram includes a change management policy, which specifies the various controls as indicated, such as initiating the CCB. Each control might have numerous subprocesses as part of the overall control. The presence of a policy is an important audit control.
Change control is an important part of project management in IT and non-IT areas -- including manufacturing and pharmaceuticals -- and can be a formal or informal process. Project managers examine change requests to determine their potential effect on the project or system. Effective change control processes are critical for incorporating necessary changes while ensuring they do not disrupt other project activities or delay progress.
Each potential change must be evaluated in relation to its potential effect on the following:
Within IT, change management and project management often operate in parallel. For example, a project's outcome, such as a scope change, could necessitate a change request. Both activities are essential tools for successfully managing an IT department.
The following are some use cases for change control in project management:
Effective change control can provide the following potential benefits for projects in almost any industry:
Change control is one aspect of the many components of change management. The following are recommended actions to take when change control and a change management activity are in place:
Many organizations develop their own change processes that address the above items. For example, the U.S. Food and Drug Administration has published its own change guidelines covering topics such as quality management, quality risk management, corrective and preventive actions, and the quality unit for evaluating change.
Task automation tools can help organizations save time and reduce risks for IT operations. Learn what types of IT automation tools can help operations teams manage multiple tasks.
11 Jun 2025