TCEQ’s data center permit freeze may reach beyond ERCOT review

Texas has paused air and water permits for data center infrastructure while ERCOT reviews a subset of qualifying projects, creating uncertainty for data center developers.

A Texas environmental regulator has halted air and water permits and other authorizations for infrastructure directly supporting data centers, leaving many unanswered questions for projects outside the state's ongoing Electric Reliability Council's grid-interconnection review.

The Texas Commission on Environmental Quality (TCEQ) has not said how the freeze will apply to projects outside a narrower State and Community Impact Request for Information (RFI) being conducted by the Electric Reliability Council of Texas (ERCOT), which applies to data center developers with at least 25 MW of peak requested load that are pursuing interconnection to the ERCOT system.

TCEQ has paused all air and water permits and other authorizations for the construction or development of infrastructure directly supporting data centers, according to Ryan Vise, the agency's director of external relations, in an email.

The permitting pause follows Gov. Greg Abbott's Sept. 21 directive to halt data center permits while ERCOT and the Texas Water Development Board conduct reviews.

The agency will incorporate findings from ERCOT's review into its regulatory evaluations and provide Abbott's office with an update on compliance by Oct. 19, Vise said.

For developers, the immediate deadlines are Oct. 12 for ERCOT's State and Community Impact RFI responses, Oct. 19 for the environmental agency's compliance update to Abbott and Dec. 10 for ERCOT's planned report to the PUC.

The deadlines are clear. The scope of the permitting freeze is not: TCEQ has yet to say whether supporting infrastructure for a data center outside ERCOT's interconnection process is also subject to the pause.

That could determine how broadly Abbott's order affects the state's data center pipeline.

Two separate processes, many unanswered questions

ERCOT is running two related but distinct information-gathering processes: a Batch Zero eligibility verification for large-load projects in the interconnection process and a separate State and Community Impact RFI for data centers.

ERCOT's RFI seeks information on grid dependency, onsite generation, water sources and consumption, cooling technology, community impacts and ownership. Responses, including supporting documentation and a notarized attestation, are due Oct. 12. ERCOT expects to report its findings to the Public Utility Commission of Texas on Dec. 10.

A state permitting decision may now depend on completion of an information and verification process whose scope, timing and outcome the developer does not completely control.
Neil Osnato, Founder, Persistence Analytics Group

The Batch Zero verification is a separate process. It seeks information, including proof of site control, financial commitment and study status. ERCOT postponed its Batch Zero transmission study while conducting the verification and said the framework is similar to what it would have done in the Batch Zero interconnection study.

 Neil Osnato, founder of Persistence Analytics Group, said the permitting pause could create a sequencing problem for developers because TCEQ's decision-making is now tied to information being gathered through ERCOT's review.

"A state permitting decision may now depend on completion of an information and verification process whose scope, timing and outcome the developer does not completely control," Osnato said.

For developers, the pause creates a new sequencing question: TCEQ says it will use ERCOT's findings in its evaluations, but has not explained what information it will rely on for projects outside ERCOT's interconnection process.

"For developers, that can create a practical sequencing problem even where other parts of a project are moving forward," Osnato said.

ERCOT does not intend to send the State and Community Impact RFI to any entity that is not interconnecting a data center to the ERCOT system, according to Trudi Webster, ERCOT's external communications manager.

What if a project changes?

The dual-review process also raises a longer-term question: whether a project must return for review if its initial underlying assumptions change.

A project that initially proposes 500 MW of demand beginning in 2028 but later becomes a 300-MW project beginning in 2030 could alter the grid infrastructure and timing assumptions made during the original review, Osnato said.

Changes in grid dependence, onsite generation, cooling technology or water use could create similar issues.

"The question should not only be: Was the evidence sufficient when the project was reviewed?" Osnato said. "It should also be: What changes are material enough that the original determination can no longer be relied upon without revalidation?"

Texas has not publicly identified what changes, if any, would trigger renewed ERCOT or TCEQ review or how they would affect a project's permitting or interconnection status.

Water data becomes a key input

Abbott's directive also ties the permitting pause to the state’s review of data center water use.

The governor previously directed the Texas Water Development Board to compel data centers to comply with water-use reporting requirements and to work with ERCOT on the data center audit.

The Sept. 21 directive says data centers must report electricity and water use and must not use water needed by local communities." Abbott also said he intends to work with the Legislature on additional measures, including eliminating financial incentives for data centers.